Supply and installation of distribution substations (11/33kV), Medium and voltage lines, transformer and connection of customers in un-electrified rural areas in Dodoma region on turnkey basis
Client: The rural energy agency
Consultant: TANESCO
Work type:
Supply, installation testing and commissioning of ;
- Transformers – 215nos
- Conductors – 4,030km
- Poles – 25,400nos
For Substations, Medium and low voltage lines and connection to customers
Commencement Date: September, 2013
Practical Completion Date: June, 2016